Paragraph 11 Soil management plan

Original text. Later amendments are not shown.

(1)

No part of the authorised development may commence until a soil management plan for that part has been submitted to and approved by the local planning authority following consultation by the undertaker with Natural England and Mining Remediation Authority.

(2)

Any soil management plan submitted for approval under sub-paragraph (1) must be in accordance with the outline soil management plan.

(3)

The construction of any part of the authorised development must be carried out in accordance with the approved soil management plan for that part.