Paragraph 14 Decommissioning and restoration

Original text. Later amendments are not shown.

(1)

Unless otherwise agreed with the local planning authority no later than 6 months prior to the intended date of decommissioning of any part of the authorised development, the undertaker must submit to the local planning authority for approval a DMP for that part.

(2)

Decommissioning must commence no later than 40 years following the date of final commissioning.

(3)

Any DMP submitted and approved under sub-paragraph (1) must be in accordance with the framework DMP.

(4)

Any DMP submitted and approved under sub-paragraph (1) must be implemented as approved.

(5)

This requirement is without prejudice to any other consents or permissions that may be required to decommission any part of the authorised development.