Paragraph 9 Surface water drainage strategy

Original text. Later amendments are not shown.

(1)

No part of the authorised development may commence until written details of the surface water drainage strategy (including means of pollution control) for that part have been submitted to and approved by the local planning authority following consultation by the undertaker with the lead relevant flood authority and the Environment Agency.

(2)

The written details under sub-paragraph (1) must be in accordance with the outline drainage strategy.

(3)

Any approved strategy must be implemented as approved.