# The Docklands Light Railway (Capacity Enhancement and 2012 Games Preparation) Order 2007, Paragraph 3


(1) Before beginning to construct any specified work, DLRL shall submit to the Agency plans of the work and such further particulars available to it as the Agency may reasonably require.
(2) Any such specified work shall not be constructed except in accordance with such plans as may be approved in writing by the Agency, or settled in accordance with paragraph 10 and, where applicable, in accordance with any conditions or requirements specified under sub-paragraph (3).
(3) Any approval of the Agency required under this paragraph—
(a) shall not be unreasonably withheld or delayed;
(b) shall be deemed to have been given if it is neither given nor refused within 2 months of the submission of plans for approval in writing and, in the case of a refusal, accompanied by a statement of the grounds of refusal; and
(c) may be given subject to such reasonable conditions or requirements as the Agency may impose—
(i) for the protection of any drainage work or water resources,
(ii) for the prevention of flooding or water pollution, or
(iii) in the discharge of its environmental and recreational duties.

---
Source: https://www.legislation.gov.uk/uksi/2007/2297/schedule/11/paragraph/3 (the official version)
Page: https://openlegislation.uk/docklands-light-railway-capacity-enhancement-and-2012-games-preparation-order-2007/schedule-11/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.