Paragraph 3
DLRL shall not in the exercise of the powers conferred by this Order permanently obstruct or interfere with pedestrian or vehicular access to the Dock unless such permanent obstruction or interference with such access is with the consent of the Board.
Nothing in article 15 (discharge of water) shall authorise DLRL—
to discharge any water directly or indirectly into the Dock; or
to carry out any works to, or make any opening in, or otherwise interfere with, the Dock (including the banks and bed thereof),
except with the consent of the Board and in accordance with plans approved by, and under the supervision (if given) of, the engineer.
DLRL shall not exercise the powers conferred by article 16 (protective works to buildings) in relation to any building forming part of the Dock, or situated on land or property of the Board forming part of the Dock, unless such exercise is with the consent of the Board.
DLRL shall not exercise the powers conferred by article 18 (power to survey and investigate land, etc.) or the powers conferred by section 11(3) of the 1965 Act in relation to the Dock unless such exercise is with the consent of the Board.
DLRL shall not exercise the powers conferred by sections 271 or 272 of the 1990 Act, as applied by Schedule 8 to this Order, so as to permanently divert any right of access to the Dock, but any such right of access may be permanently diverted with the consent of the Board.
The consent of the Board pursuant to any of sub-paragraphs (1), (3), (4) and (5) and the approval of plans under sub-paragraph (2) shall not be unreasonably withheld or delayed but may be given subject to reasonable conditions which in the case of article 15 (discharge of water) may include conditions—
specifying the maximum volume of water which may be discharged in any period; and
authorising the Board on giving reasonable notice (except in an emergency, when the Board may require immediate suspension) to DLRL to require DLRL to suspend the discharge of water or reduce the flow thereof where this is necessary by reason of any operational requirement of the Board and where a reasonable alternative is available to enable DLRL to discharge the water in question during the period of the suspension.