# The Docklands Light Railway (Capacity Enhancement) Order 2005, Paragraph 22

Extent: E+W+S

Any approval of the specified undertaker required under paragraph 21—
(a) may be given subject to reasonable conditions for any purpose mentioned in paragraph 23;
(b) shall not be unreasonably withheld; and
(c) shall be deemed to have been given if it is neither given nor refused within 56 days of the submission of plans for approval.

---
Source: https://www.legislation.gov.uk/uksi/2005/3105/schedule/13/paragraph/22 (the official version)
Page: https://openlegislation.uk/docklands-light-railway-capacity-enhancement-order-2005/schedule-13/paragraph-22
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.