# The Docklands Light Railway (Capacity Enhancement) Order 2005, Paragraph 25

Extent: E+W+S

If within 42 days after the submission to it of any plans under paragraph 19, in consequence of the works proposed by DLRL the specified undertaker reasonably requires the removal of any apparatus and gives written notice to DLRL of that requirement, the foregoing provisions of this Schedule shall have effect as if the removal of such apparatus had been required by the specified undertaker under paragraph 8.

---
Source: https://www.legislation.gov.uk/uksi/2005/3105/schedule/13/paragraph/25 (the official version)
Page: https://openlegislation.uk/docklands-light-railway-capacity-enhancement-order-2005/schedule-13/paragraph-25
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.