# The Docklands Light Railway (Capacity Enhancement) Order 2005, Part 2: STATION WORKS

Extent: E+W+S

(1)
(2)
(3)
Location
Number of land shown on the deposited plans
Purpose for which land may be acquired or used
London borough of Tower Hamlets
Shadwell Station
127, 128, 129, 130, 131, 132, 133
Provision of platform extension, emergency stairs, canopy extension, working sites and access
Limehouse Station
219, 220, 221, 222, 223, 224, 226, 227, 228, 229, 230, 231, 232, 233, 234, 235, 236, 237, 238, 239, 240, 241, 242, 243, 245, 246, 247, 248, 249, 250, 251, 253, 254, 255, 256, 257, 259, 260, 261, 262, 263
Provision of platform extension, stairs, lift, canopy, substation, pile strengthening, working sites and access
Westferry Station
274, 275, 276, 277, 278, 279, 280, 281, 282, 283, 284, 285, 286, 287, 288, 289, 290, 291, 292, 293, 294, 295, 296, 297, 298, 300, 301, 302, 303, 304, 306, 307, 308
Provision of platform extension, stairs, lift, canopy, pile strengthening, working sites and access
West India Quay Station
394, 395, 396, 398, 399, 400, 401, 402, 403, 404, 405, 406, 407
Provision of platform extension, pile strengthening, working sites and access
Crossharbour Station
694, 695, 696, 697, 698, 699, 700, 701, 702, 703, 704, 705, 706, 707, 708, 709, 710, 711, 712
Provision of platform extension, stairs, canopy extension, pile strengthening, subway, working sites and access
London borough of Greenwich
Greenwich Station
737, 739, 740, 741, 743, 744, 745, 748, 749, 750, 751, 752, 753, 754
Provision of platform extension, canopy extension, emergency escape stair modifications, removal of existing stairs, pile strengthening, working sites and access
Deptford Bridge Station
780, 781
Provision of platform extension, canopies, stairs, pile strengthening, working sites and access
London borough of Lewisham
Deptford Bridge Station
782, 783, 784, 785, 786, 787, 788, 790, 793
Provision of platform extension, canopies, stairs, pile strengthening, working sites and access
Elverson Road
800, 804, 805
Provision of platform extension, canopies, working sites and access
Lewisham Station
822, 823, 824, 825, 827, 828, 830, 831, 832, 833, 834, 835, 836, 837, 838, 839, 840, 841, 842, 843, 844, 845, 846, 847, 848, 851, 852, 853, 854, 855
Provision of platform extension, new stairs, stair modifications, structural modifications to existing station, canopy extension

---
Source: https://www.legislation.gov.uk/uksi/2005/3105/schedule/2/part/2 (the official version)
Page: https://openlegislation.uk/docklands-light-railway-capacity-enhancement-order-2005/schedule-2/part-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.