# The Docklands Light Railway (Silvertown and London City Airport Extension) Order 2002, Paragraph 24


(1) This paragraph shall apply to EMI only to the extent that such EMI is not attributable to any change to the Underground companies’ apparatus carried out after approval of plans under paragraph 18(1) above for the relevant part of the authorised works giving rise to EMI (unless DLRL has been given notice in writing before the approval of those plans of the intention to make such change).
(2) Subject to sub-paragraph (4) below, DLRL shall in the design and construction of the authorised works take all measures necessary to prevent EMI and shall establish with LUL (both parties acting reasonably) appropriate arrangements to verify their effectiveness.
(3) In order to facilitate DLRL’s compliance with sub-paragraph (2) above—
(a) DLRL shall consult with LUL as early as reasonably practicable to identify all the Underground companies’ works and apparatus which may be at risk of EMI, and thereafter shall continue to consult with LUL (both before and after formal submission of plans under paragraph 18(1) above) to identify all potential causes of EMI and the measures required to eliminate them;
(b) the Underground companies shall make available to DLRL all information in their possession reasonably requested by DLRL in respect of the Underground companies’ works and apparatus identified pursuant to paragraph (a) above; and
(c) the Underground companies shall allow DLRL reasonable facilities for the inspection of the Underground companies’ works and apparatus identified pursuant to paragraph (a) above.
(4) In any case where it is established that EMI can only reasonably be prevented by modifications to the Underground companies’ works and apparatus, the Underground companies shall not withhold their consent unreasonably to modifications of the Underground companies’ works and apparatus, but the means of prevention and the method of their execution shall be selected in LUL’s reasonable discretion and in relation to such modifications paragraph 18(1) above shall have effect subject to this sub-paragraph.
(5) If at any time prior to the commencement of regular revenue-earning train operations on the new railways comprised in the authorised works and notwithstanding any measures adopted pursuant to sub-paragraph (2) above, the testing or commissioning of the authorised works causes EMI then DLRL shall immediately upon receipt of notification by LUL of such EMI either in writing or communicated orally (such oral communication to be confirmed in writing as soon as reasonably practicable after it has been issued) forthwith cease to use (or procure the cessation of use of) DLRL’s apparatus causing such EMI until all measures necessary have been taken to remedy such EMI by way of modification to the source of such EMI or (in the circumstances, and subject to the consent, specified in sub-paragraph (4) above) to the Underground companies’ works and apparatus.
(6) In the event of EMI having occurred—
(a) DLRL shall afford reasonable facilities to the Underground companies for access to DLRL’s apparatus in the investigation of such EMI;
(b) the Underground companies shall afford reasonable facilities to DLRL for access to the Underground companies’ works and apparatus in the investigation of such EMI; and
(c) the Underground companies shall make available to DLRL any additional material information in their possession reasonably requested by DLRL in respect of the Underground companies’ works and apparatus or such EMI.
(7) Where the Underground companies approve modifications to the Underground companies’ works and apparatus pursuant to sub-paragraphs (4) or (5) above—
(a) the Underground companies shall allow DLRL reasonable facilities for the inspection of the relevant part of the Underground companies’ works and apparatus;
(b) any modifications to the Underground companies’ works and apparatus approved pursuant to those sub-paragraphs shall be carried out and completed by DLRL in accordance with paragraph 19 above.
(8) To the extent that it would not otherwise do so, the indemnity in paragraph 26(1) below shall apply to the costs and expenses reasonably incurred or losses suffered by the Underground companies through the implementation of the provisions of this paragraph (including costs incurred in connection with the consideration of proposals, approval of plans, supervision and inspection of works and facilitating access to the Underground companies’ works and apparatus) or in consequence of any EMI to which sub-paragraph (5) above applies.
(9) For the purpose of paragraph 23(a) above any modifications to the Underground companies’ works and apparatus under this paragraph shall be deemed to be protective works referred to in that paragraph.
(10) In relation to any dispute arising under this paragraph the reference in article 48 above to the Institution of Civil Engineers shall be read as a reference to the Institution of Electrical Engineers.

---
Source: https://www.legislation.gov.uk/uksi/2002/1066/schedule/11/paragraph/24 (the official version)
Page: https://openlegislation.uk/docklands-light-railway-silvertown-and-london-city-airport-extension-order-2002/schedule-11/paragraph-24
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.