{
  "url": "https://openlegislation.uk/docklands-light-railway-silvertown-and-london-city-airport-extension-order-2002/schedule-13/paragraph-10",
  "json_url": "https://openlegislation.uk/docklands-light-railway-silvertown-and-london-city-airport-extension-order-2002/schedule-13/paragraph-10.json",
  "legislation": "uksi/2002/1066",
  "legislation_title": "The Docklands Light Railway (Silvertown and London City Airport Extension) Order 2002",
  "legislation_url": "https://openlegislation.uk/docklands-light-railway-silvertown-and-london-city-airport-extension-order-2002",
  "path": "schedule/13/paragraph/10",
  "kind": "paragraph",
  "number": "10",
  "heading": null,
  "text": "The approval of plans supplied under paragraph 9 above shall not be unreasonably withheld and if, within 2 months of such plans being supplied to the Environment Agency, the Environment Agency does not indicate in writing its disapproval and the grounds of its disapproval, it shall be deemed to have approved the plans as supplied.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2002/1066/schedule/13/paragraph/10",
    "retrieved_at": "2026-10-29T07:00:14.656841+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}