# The Dogger Bank Creyke Beck Offshore Wind Farm (Amendment) Order 2020, Article 4: Amendment to Part 3 (Requirements) of Schedule 1 (Authorised project)


(1) Part 3 (Requirements) of Schedule 1 (Authorised project) is amended as follows.
(2) In paragraph 4(2), for the words “must be of such a size that if they were installed to the maximum permitted gross generating capacity specified for those works the total rotor-swept area for each Work No. would not exceed 4.35 square kilometres”, substitute “must not exceed a total rotor-swept area for each Work No. of 4.35 square kilometres”.

---