# The Dogger Bank Creyke Beck Offshore Wind Farm (Amendment) Order 2022, Note: Explanatory note


(This note is not part of the Order)
This Order amends the Dogger Bank Creyke Beck Offshore Wind Farm Order 2015, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 2 of Schedule 6 to the Planning Act 2008. This Order increases the maximum amount of energy that can be used by piling hammers to install pin piles and monopiles that secure wind turbine generators and offshore platforms to the ocean floor.

---
Source: https://www.legislation.gov.uk/uksi/2022/681/note (the official version)
Page: https://openlegislation.uk/dogger-bank-creyke-beck-offshore-wind-farm-amendment-order-2022/note
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.