# The Dogger Bank Creyke Beck Offshore Wind Farm (Amendment) Order 2025, Article 9: Amendment to Part 3 (Requirements) of Schedule 1 (Authorised Project)


Schedule 1 (Authorised Project), Part 3 (Requirements), paragraph 25 is amended as follows—
(a) in paragraph 25(1)—
(i) for “Work No. 7” substitute “the Project A converter station”;
(ii) after “must”, delete “each or together”;
(iii) after “35 decibels”, insert “(including when taken as a whole with the Project B converter station)”.
(b) after paragraph 25(1) insert—
“(1A) The noise emanating from the operation of the Project B converter station (including transformers, cooling fans, switch gear and power lines) must not exceed operational noise levels of 35 decibels (including when taken as a whole with the Project A converter station) as given in BS4142 at the nearest receptors identified on the works plans as follows (with grid references shown as easting: northing)—
(a) Halfway House (504796; 436331);
(b) Model Farm (504011; 436576);
(c) Poplar Farm (503727; 435672); and
(d) Wanlass Farm (504385; 435168).”;
(c) in paragraph 25(3), after “in relation to the”, insert “Project A”;
(d) after paragraph 25(3) insert—
“(3A) All standby generator testing in relation to the Project B onshore works must be undertaken between 9 a.m. and 5 p.m. on Monday to Saturday, and not at all on Sundays or public or bank holidays, unless otherwise agreed in writing with the relevant planning authority.”.

---
Source: https://www.legislation.gov.uk/uksi/2025/1264/article/9 (the official version)
Page: https://openlegislation.uk/dogger-bank-creyke-beck-offshore-wind-farm-amendment-order-2025/article-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.