# The Dogger Bank Creyke Beck Offshore Wind Farm (Correction) Order 2015, Schedule


(1) Where correction is to be made
(2) Text to be omitted
(3) Text to be substituted
Article 2(1), definition of “offshore works plans”
Omit: “the works plans”
Substitute: “the offshore works plans”
Article 23(2)
Omit: “on 11th March 2020”
Substitute: “after 11th March 2020”
Article 23(2)
Omit: “before that date”
Substitute: “on or before that date”

---
Source: https://www.legislation.gov.uk/uksi/2015/1742/schedule (the official version)
Page: https://openlegislation.uk/dogger-bank-creyke-beck-offshore-wind-farm-correction-order-2015/schedule
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.