# The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015, Paragraph 10: Offshore decommissioning

Extent: E+W+S

No offshore works must commence until a written decommissioning programme, including addressing the possibility of abandonment or decay, in compliance with any notice served on the undertaker by the Secretary of State pursuant to section 105(2) of the 2004 Act has been submitted to the Secretary of State for approval.

---