# The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015, Paragraph 11: Stages of authorised development onshore

Extent: E+W+S

(1) The onshore works must not commence until a written scheme setting out the phasing of construction of each stage of the onshore works has been submitted to and approved in writing by the relevant planning authority.
(2) The onshore works must be carried out in accordance with the approved scheme.

---
Source: https://www.legislation.gov.uk/uksi/2015/318/schedule/1/paragraph/11 (the official version)
Page: https://openlegislation.uk/dogger-bank-creyke-beck-offshore-wind-farm-order-2015/schedule-1/paragraph-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.