(1) The onshore works must be carried out in accordance with the following plans submitted with the application—
(a) the onshore Order limits plan; and
(b) the onshore works plans.
(2) Sub-paragraph (1) does not apply—
(a) to the extent that any part of a plan referred to that sub-paragraph is indicative or expressly states that it does not show details for approval; or
(b) where details in such a plan are amended with the written approval of the relevant planning authority; and such approval may be given only in relation to immaterial changes that are within the scope of the works assessed in the environmental statement and fall within the Order limits.
(3) Where amended details are approved pursuant to this Requirement, those details are deemed to be substituted for the corresponding details previously approved.

---
Source: https://www.legislation.gov.uk/uksi/2015/318/schedule/1/paragraph/13 (the official version)
Page: https://openlegislation.uk/dogger-bank-creyke-beck-offshore-wind-farm-order-2015/schedule-1/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.