# The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015, Paragraph 26: Control of artificial light emissions

Extent: E+W+S

(1) The Project A converter station works must not be brought into operation until a written scheme for the management and mitigation of artificial light emissions during the operation of Work No. 7 has been submitted to and approved in writing by the relevant planning authority following consultation with the relevant statutory nature conservation body.
(2) The approved scheme for the management and mitigation of artificial light emissions under paragraph (1) must be implemented and maintained during the operation of the Project A onshore works.
(3) The Project B converter station works must not be brought into operation until a written scheme for the management and mitigation of artificial light emissions during the operation of the Project B converter station works has been submitted to and approved by the relevant planning authority following consultation with the relevant statutory nature conservation body.
(4) The approved scheme for the management and mitigation of artificial light emissions under paragraph (3) must be implemented and maintained during the operation of the Project B onshore works.

---
Source: https://www.legislation.gov.uk/uksi/2015/318/schedule/1/paragraph/26 (the official version)
Page: https://openlegislation.uk/dogger-bank-creyke-beck-offshore-wind-farm-order-2015/schedule-1/paragraph-26
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.