# The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015, Paragraph 33: Amendments to approved details

Extent: E+W+S

(1) Where a Requirement requires the authorised development to be carried out in accordance with details approved by the relevant planning authority or another person, the approved details must be taken to include any amendments that have been approved in writing by the relevant planning authority or other person.
(2) Any amendment to or variation from the approved details must be in accordance with the principles and assessments set out in the environmental statement.

---