# The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015, Part 2: Ancillary works

Extent: E+W+S

In relation to the Project A offshore works and the Project B offshore works, works comprising—
(a) temporary landing places, moorings or other means of accommodating vessels in the construction or maintenance of the authorised development;
(b) temporary or permanent buoys, beacons, fenders and other navigational warning or ship impact protection works;
(c) temporary works for the protection of land or structures affected by the authorised development;
(d) cable protection, scour protection or dredging;
(e) cable route preparation works including boulder removal and obstruction clearance, dredging and pre-sweeping; and
(f) the removal, reconstruction or alteration of the position of subsea cables and pipelines.

---
Source: https://www.legislation.gov.uk/uksi/2015/318/schedule/1/part/2 (the official version)
Page: https://openlegislation.uk/dogger-bank-creyke-beck-offshore-wind-farm-order-2015/schedule-1/part-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.