# The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015, Paragraph 9: Pre-construction plans and documentation

Extent: E+W+S

(1) Each programme, statement, plan, protocol, scheme or details required to be approved under Condition 8, and the arrangements required to be approved under Condition 4, must be submitted for approval at least 4 months before the intended commencement of construction, except where otherwise stated or unless otherwise agreed in writing by the MMO.
(2) The licensed activities must be carried out in accordance with the programme, statement, plan, protocol, scheme or details approved under Condition 8.

---