# The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015, Paragraph 21

Extent: E+W+S

The undertaker must, no later than 28 days from the date that the plans are certified by the Secretary of State in accordance with article 42 (certification of plans and documents, etc.), provide to Network Rail a set of plans that relate to the specified works in the form of a computer disc with read-only memory.

---
Source: https://www.legislation.gov.uk/uksi/2015/318/schedule/12/paragraph/21 (the official version)