# The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015, Paragraph 8

Extent: E+W+S

(1) Nothing in paragraphs 4(5), 5(3), 6 and 7(3) and (4) authorises the Agency to execute works on or affecting the authorised development without the prior consent in writing of the undertaker.
(2) Consent under sub-paragraph (1) must not be unreasonably withheld or delayed, and the undertaker is deemed to have given its consent if it has not refused consent within 2 months of receiving a written request by the Agency.

---
Source: https://www.legislation.gov.uk/uksi/2015/318/schedule/12/part/5/paragraph/8 (the official version)