# The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015, Paragraph 19: Aids to navigation

Extent: E+W+S

The undertaker must keep Trinity House and the MMO informed of progress of the authorised scheme seaward of MHWS including—
(a) notice of commencement of construction of the authorised scheme within 24 hours of commencement having occurred;
(b) notice within 24 hours of any aids to navigation being established by the undertaker; and
(c) notice within 5 working days of completion of construction of the authorised scheme.

---
Source: https://www.legislation.gov.uk/uksi/2015/318/schedule/9/paragraph/19 (the official version)
Page: https://openlegislation.uk/dogger-bank-creyke-beck-offshore-wind-farm-order-2015/schedule-9/paragraph-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.