Works within the Order limits which have been subject to an environmental assessment recorded in the environmental statement comprising—
(a) intrusive ground investigations including the making of boreholes and trial pits;
(b) temporary landing places, moorings or other means of accommodating or anchoring vessels in the construction or maintenance of the authorised development;
(c) temporary or permanent buoys, beacons, fenders and other navigational warning or ship impact protection works; and
(d) temporary works for the benefit or protection of land, groundwater, watercourses or structures affected by the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2026/577/schedule/1/paragraph/2 (the official version)
Page: https://openlegislation.uk/dogger-bank-south-east-and-west-offshore-wind-farms-order-2026/schedule-1/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.