(1) The licensed activities or any phase of those activities must not commence until an ornithological monitoring plan in accordance with condition 24(1)(b) including any information on indirect effects, setting out the circumstances in which ornithological monitoring will be required and the monitoring to be carried out in such circumstances has been submitted to and approved in writing by the MMO, in consultation with the relevant statutory nature conservation body.
(2) The ornithological monitoring plan must be submitted in writing to the MMO no later than six months prior to the first pre-construction survey.
(3) The undertaker must carry out any monitoring agreed under sub-paragraph (1) and provide the agreed reports to the MMO in the agreed format in accordance with the agreed timetable, unless otherwise agreed in writing with the MMO in consultation with the relevant statutory nature conservation body.
(4) All monitoring reports must be made publicly available and submitted to relevant evidence databases (as agreed with the MMO) no later than six months following written approval of the relevant report by the MMO under this condition, completion of the monitoring required unless otherwise agreed in writing by the MMO, in consultation with the relevant statutory nature conservation body.

---
Source: https://www.legislation.gov.uk/uksi/2026/577/schedule/10/paragraph/38 (the official version)
Page: https://openlegislation.uk/dogger-bank-south-east-and-west-offshore-wind-farms-order-2026/schedule-10/paragraph-38
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.