# The Dogger Bank South East and West Offshore Wind Farms Order 2026, Paragraph 33: Completion of construction


(1) The undertaker must submit a close out report to the MMO, the MCA, Trinity House, UKHO and the relevant statutory nature conservation body within three months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include the following details—
(a) the final number of installed wind turbine generators;
(b) the installed wind turbine generator parameters;
(c) as built plans;
(d) latitude and longitude coordinates of the centre point of the location for each wind turbine generator and offshore accommodation platform, provided as Geographical Information System data referenced to WGS84 datum; and
(e) latitude and longitude coordinates of the array cables, provided as Geographical Information System data referenced to WGS84 datum.
(2) Following completion of construction, no further construction activities can be undertaken under this licence.

---
Source: https://www.legislation.gov.uk/uksi/2026/577/schedule/11/paragraph/33 (the official version)
Page: https://openlegislation.uk/dogger-bank-south-east-and-west-offshore-wind-farms-order-2026/schedule-11/paragraph-33
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.