# The Dogger Bank South East and West Offshore Wind Farms Order 2026, Paragraph 16: Notifications and inspections


(1) The undertaker must ensure that—
(a) a copy of this licence (issued as part of the grant of the Order) and any subsequent amendments or revisions to it is provided to—
(i) all agents and contractors notified to the MMO in accordance with condition 17;
(ii) the masters and transport managers responsible for the vessels notified to the MMO in accordance with condition 17; and
(b) the undertaker must confirm in writing to the MMO within 28 days of a copy of this licence and any subsequent amendments or revisions to it being provided to the persons listed in sub-paragraph (1)(a) that the required information has been provided.
(2) Only those persons and vessels notified to the MMO in accordance with condition 17 are permitted to carry out the licensed activities.
(3) Copies of this licence must also be available for inspection at the following locations—
(a) the undertaker’s registered address;
(b) any site office located at or adjacent to the construction site and used by the undertaker or its agents and contractors responsible for the loading, transportation or deposit of the authorised deposits; and
(c) on board each vessel and at the office of any transport manager with responsibility for vessels from which authorised deposits or removals are to be made.
(4) The documents referred to in sub-paragraph (1) must be available for inspection by an authorised enforcement officer at the locations set out in sub-paragraph (3).
(5) The undertaker must provide access, and if necessary appropriate transportation, to the offshore construction site or any other associated works or vessels to facilitate any inspection that the MMO considers necessary to inspect the works during the construction and operation of the authorised scheme.
(6) The undertaker must inform the MMO Local Office in writing at least fourteen days prior to the commencement of the licensed activities or any part of them and within five days of the completion of the licensed activity.
(7) The undertaker must inform the Kingfisher Information Service of Seafish by email to kingfisher@seafish.co.uk of details of the vessel routes, timings and locations relating to the construction of the authorised scheme or relevant part—
(a) at least fourteen days prior to the commencement of offshore activities, for inclusion in the Kingfisher Fortnightly Bulletin and offshore hazard awareness data;
(b) as soon as reasonably practicable and no later than 24 hours of completion of the DBS East Project offshore works,
and confirmation of notification must be provided to the MMO within five days.
(8) The undertaker must ensure that a local notification to mariners is issued at least 14 days prior to the commencement of the authorised scheme or any part thereof advising of the start date of each of Work Nos. 2A, 3A, 7A and 8A and the expected vessel routes from the construction ports to the relevant location. Copies of all notices must be provided to the MMO, MCA and UKHO within five days.
(9) The undertaker must ensure that local notifications to mariners are updated and reissued at weekly intervals during construction activities and at least five days before any planned operations (unless otherwise agreed in writing by the MMO) and maintenance works and supplemented with VHF radio broadcasts agreed with the MCA in accordance with the construction programme and monitoring plan approved under condition 13(1)(b). Copies of all notices must be provided to the MMO, UKHO and the MCA within five days.
(10) The undertaker must notify UKHO and the MCA of the commencement (within ten days), progress and completion of construction (within ten days) of the licensed activities in order that all necessary amendments to nautical and aeronautical charts are made and the undertaker must send a copy of such notifications to the MMO within five days of the notification.
(11) In case of damage to, or destruction or decay of, the authorised scheme or any part thereof, excluding the exposure of cables, the undertaker must as soon as reasonably practicable and no later than 24 hours following the undertaker becoming aware of any such damage, destruction or decay, notify the MMO, the MMO Local Office, MCA, Trinity House, the Kingfisher Information Service of Seafish and UKHO.
(12) In case of the exposure of cables on or above the seabed, the undertaker must within three days following identification of a potential cable exposure, notify mariners and inform the Kingfisher Information Service of Seafish of the location and extent of exposure. Copies of all notices must be provided to the MMO, MCA, Trinity House, and UKHO within five days.
(13) The undertaker must notify the MMO in writing a minimum of five days in advance of the commencement of each discrete incident of cable repair, replacement, or protection replenishment activity. Such a notification must include proposed timings and a description of proposed methodologies.
(14) The undertaker must ensure that the MMO, the MMO Local Office, local mariners, local fishermen’s organisations and the Source Data Receipt Team at the UK Hydrographic Office, Taunton, Somerset, TA1 2DN (sdr@ukho.gov.uk) are notified within five days of completion of each instance of cable repair, replacement or protection replenishment activity.

---
Source: https://www.legislation.gov.uk/uksi/2026/577/schedule/12/paragraph/16 (the official version)
Page: https://openlegislation.uk/dogger-bank-south-east-and-west-offshore-wind-farms-order-2026/schedule-12/paragraph-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.