# The Dogger Bank South East and West Offshore Wind Farms Order 2026, Paragraph 32: Collaboration


(1) Prior to submission of plans and documentation required to be submitted to the MMO for approval in accordance with conditions 14 and 15, the undertaker must provide a copy of the relevant plans and documentation to DBSWL and allow a reasonable period of time to enable DBSWL to provide any comments on the plans and documentation to the undertaker.
(2) The plans and documentation submitted to the MMO for approval in accordance with conditions 14 and 15 must be accompanied by any comments received by the undertaker from DBSWL in accordance with sub-paragraph (1) or a statement from the undertaker confirming that no such comments were received.

---
Source: https://www.legislation.gov.uk/uksi/2026/577/schedule/12/paragraph/32 (the official version)
Page: https://openlegislation.uk/dogger-bank-south-east-and-west-offshore-wind-farms-order-2026/schedule-12/paragraph-32
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.