# The Dogger Bank South East and West Offshore Wind Farms Order 2026, Paragraph 27: Completion of construction


(1) The undertaker must submit a close out report to the MMO, the MCA, Trinity House, UKHO and the relevant statutory nature conservation body within three months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include as built plans and details of the latitude and longitude co-ordinates of the export cables, provided as Geographical Information System data referenced to WGS84 datums.
(2) Following completion of construction, no further construction activities can be undertaken under this licence.

---