The undertaker, in the case of the powers conferred by article 17 (protective work to buildings), must exercise those powers so as not to obstruct or render less convenient the access to any apparatus, the Wanlass Beck Site, the North Humber to High Marnham Site or to the Birkhill Wood Site without the prior written consent of National Grid Electricity Transmission Plc (such consent not to be unreasonably withheld or delayed).

---