# The Dogger Bank South East and West Offshore Wind Farms Order 2026, Paragraph 10: Kittiwake CIMP


The undertaker must implement the measures set out in the kittiwake CIMP approved by the Secretary of State, unless otherwise agreed in writing by the Secretary of State in consultation with the relevant statutory nature conservation body and, where appropriate, the MMO and/or the relevant planning authority for the area in which the onshore artificial nesting structure is located.

---
Source: https://www.legislation.gov.uk/uksi/2026/577/schedule/18/paragraph/10 (the official version)
Page: https://openlegislation.uk/dogger-bank-south-east-and-west-offshore-wind-farms-order-2026/schedule-18/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.