# The Dogger Bank South East and West Offshore Wind Farms Order 2026, Paragraph 15: Kittiwake CIMP


The kittiwake CIMP approved under this Schedule includes any amendments that may subsequently be approved in writing by the Secretary of State. Any amendments to or variations of the approved kittiwake CIMP must be in accordance with the principles set out in the outline kittiwake CIMP and the kittiwake compensation plan and may only be approved where it has been demonstrated to the satisfaction of the Secretary of State that it is unlikely to give rise to any materially new or materially different environmental effects from those considered in the kittiwake compensation plan.

---
Source: https://www.legislation.gov.uk/uksi/2026/577/schedule/18/paragraph/15 (the official version)
Page: https://openlegislation.uk/dogger-bank-south-east-and-west-offshore-wind-farms-order-2026/schedule-18/paragraph-15
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.