# The Dogger Bank South East and West Offshore Wind Farms Order 2026, Paragraph 20: Guillemot CIMP


Where the undertaker elects to submit a Guillemot CIMP under paragraph 18(1)(b) or paragraph 18(1)(c), Work No. 1A and 1B may not commence construction until a plan for the work of the GCSG has been submitted to and approved by the Secretary of State. Such plan to include—
(a) terms of reference of the GCSG;
(b) details of the membership of the GCSG which must include the relevant statutory nature conservation body and, where appropriate, the MMO and/or the relevant planning authority as core members;
(c) details of the proposed schedule of meetings, timetable for preparation of the Guillemot CIMP and reporting and review periods; and
(d) the dispute resolution mechanism.

---
Source: https://www.legislation.gov.uk/uksi/2026/577/schedule/18/paragraph/20 (the official version)
Page: https://openlegislation.uk/dogger-bank-south-east-and-west-offshore-wind-farms-order-2026/schedule-18/paragraph-20
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

