# The Dogger Bank South East and West Offshore Wind Farms Order 2026, Paragraph 20: Construction hours for the onshore works


(1) Construction work for the onshore works must only take place between 0700 hours and 1900 hours Monday to Saturday, with no activity on Sundays, bank holidays or public holidays, except as specified in sub-paragraphs (2) to (4).
(2) Outside the hours specified in sub-paragraph (1), construction work may be undertaken for essential activities including but not limited to—
(a) continuous periods of operation that are required as assessed in the environmental statement, such as concrete pouring, drilling, and pulling cables (including fibre optic cables) through ducts and trenchless crossings;
(b) internal fitting out works associated with the onshore HVDC converter station buildings comprised within Work Nos. 25A or 26A and 26B;
(c) delivery of abnormal loads to the onshore works that may otherwise cause congestion on the local road network;
(d) the testing or commissioning of any electrical plant installed as part of the onshore works;
(e) security monitoring; or
(f) activity necessary in the instance of an emergency or where there is an immediate risk to persons, the environment, delivery of electricity, or property.
(3) Save for emergency works, full details, including but not limited to type of activity, vehicle movements and type, timing and duration and any proposed mitigation, of all essential construction activities under sub-paragraph (2) and undertaken outside of the hours specified in sub-paragraph (1) must be approved by the relevant planning authority in writing in advance, and must be carried out within the agreed time.
(4) In the event of an emergency, notification of that emergency must be given to the relevant planning authority and the relevant highway authority as soon as reasonably practicable.
(5) For the purposes of this requirement “emergency” means a situation where, if the relevant action is not taken, there will be adverse health, safety, security or environmental consequences that in the reasonable opinion of the undertaker would outweigh the adverse effects to the public (whether individuals, classes or generally as the case may be) of taking that action.

---
Source: https://www.legislation.gov.uk/uksi/2026/577/schedule/2/paragraph/20 (the official version)
Page: https://openlegislation.uk/dogger-bank-south-east-and-west-offshore-wind-farms-order-2026/schedule-2/paragraph-20
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.