# The Dogger Bank South East and West Offshore Wind Farms Order 2026, Paragraph 35: Onshore collaboration


DBSEL and DBSWL must—
(a) before submitting any plan or document required to be submitted for approval under the requirements to the relevant discharging authority, provide a copy of the plan or document to the other undertaker and allow a reasonable period of time to enable the other undertaker to provide comments on the relevant plans and documentation; and
(b) when submitting any plan or document referred to in sub-paragraph (a) for approval, submit to the relevant discharging authority any comments duly received from the other undertaker or a statement conﬁrming that no such comments were received.

---
Source: https://www.legislation.gov.uk/uksi/2026/577/schedule/2/paragraph/35 (the official version)
Page: https://openlegislation.uk/dogger-bank-south-east-and-west-offshore-wind-farms-order-2026/schedule-2/paragraph-35
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.