# The Dogger Bank South East and West Offshore Wind Farms Order 2026, Paragraph 7: Offshore decommissioning


(1) The DBS East Project offshore works must not be commenced until a written decommissioning programme in compliance with any notice served upon the undertaker by the Secretary of State pursuant to section 105(2) of the 2004 Act (requirement to prepare decommissioning programmes) has been submitted to the Secretary of State for approval.
(2) The DBS West Project offshore works must not be commenced until a written decommissioning programme in compliance with any notice served upon the undertaker by the Secretary of State pursuant to section 105(2) of the 2004 Act (requirement to prepare decommissioning programmes) has been submitted to the Secretary of State for approval.

---
Source: https://www.legislation.gov.uk/uksi/2026/577/schedule/2/paragraph/7 (the official version)
Page: https://openlegislation.uk/dogger-bank-south-east-and-west-offshore-wind-farms-order-2026/schedule-2/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.