# The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) (No. 2) Order 2020, Article 17: Amendments to Part 3 (requirements) of Schedule 1 (authorised project)


In paragraph 22(1) of Part 3 of Schedule 1 for “All landscaping works must be carried out in accordance with the landscaping scheme approved”, substitute “The landscaping works for each stage must be carried out in accordance with the relevant landscaping scheme approved for that stage”.

---
Source: https://www.legislation.gov.uk/uksi/2020/1389/article/17 (the official version)
Page: https://openlegislation.uk/dogger-bank-teesside-a-and-b-offshore-wind-farm-amendment-no-2-order-2020/article-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.