# The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2020, Article 3: Amendments to Part 1 (Authorised Development) of Schedule 1 (Authorised Project)


(1) Part 1 (Authorised Development) of Schedule 1 (Authorised Project) is amended as follows.
(2) In paragraph 1, in the description of Project A offshore works, in sub-paragraph (a) of the description of Work No 1A, for “up to 1.2 gigawatts” substitute “more than 100 megawatts”.

---
Source: https://www.legislation.gov.uk/uksi/2020/851/article/3 (the official version)
Page: https://openlegislation.uk/dogger-bank-teesside-a-and-b-offshore-wind-farm-amendment-order-2020/article-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.