# The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2020, Article 4: Amendment to Part 3 (Requirements) of Schedule 1 (Authorised project)


(1) Part 3 (Requirements) of Schedule 1 (Authorised Project) is amended as follows.
(2) In paragraph 3(1)(b), for “215 metres”, substitute “280 metres”.
(3) In paragraph 41, before sub-paragraph (1), insert—
“(A1) No Project A offshore works, or activities associated with them, that may have a significant effect on the Southern North Sea Special Area of Conservation may commence until the review of consents has been completed and the Secretary of State has affirmed, modified or revoked the decision in respect of the Project A offshore works or activities associated with them under regulation 33(4) of the Conservation of Offshore Marine Habitats and Species Regulations 2017.”.

---
Source: https://www.legislation.gov.uk/uksi/2020/851/article/4 (the official version)
Page: https://openlegislation.uk/dogger-bank-teesside-a-and-b-offshore-wind-farm-amendment-order-2020/article-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.