# The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015, Article 16: Access to works

Extent: E+W+S

The undertaker may, for the purposes of the authorised project,—
(a) form and lay out means of access, or improve existing means of access, in the locations specified in Schedule 4 (access to works);
(b) with the approval of the relevant planning authority after consultation with the highway authority, form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires.

---
Source: https://www.legislation.gov.uk/uksi/2015/1592/article/16 (the official version)
Page: https://openlegislation.uk/dogger-bank-teesside-a-and-b-offshore-wind-farm-order-2015/article-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.