(1) Where an application is made to the relevant planning authority or to the relevant planning authority for the port for any consent, agreement or approval required by a Requirement, the following provisions apply in respect of that application as they would if the consent, agreement or approval so required were required by a condition imposed on a grant of planning permission—
(a) sections 78 and 79 of the 1990 Act (right of appeal in relation to planning decisions);
(b) any orders, rules or regulations that make provision in relation to a consent, agreement or approval of a local planning authority required by a condition imposed on a grant of planning permission.
(2) For the purposes of paragraph (1), orders, rules and regulations make provision in relation to a consent, agreement or approval of a local planning authority required by a condition imposed on a grant of planning permission in so far as they make provision in relation to—
(a) an application for such a consent, agreement or approval;
(b) the grant or refusal of such an application;
(c) a failure to give notice of a decision on such an application.
(3) For the purposes of the application of section 262 of the 1990 Act (meaning of “statutory undertaker”) to appeals pursuant to this article, the undertaker is deemed to be a holder of a licence under section 6 of the Electricity Act 1989.
(4) Nothing in paragraph (1)(b) affects the application of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2009.

---
Source: https://www.legislation.gov.uk/uksi/2015/1592/article/6 (the official version)
Page: https://openlegislation.uk/dogger-bank-teesside-a-and-b-offshore-wind-farm-order-2015/article-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.