# The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015, Paragraph 16: Offshore safety management

Extent: E+W+S

(1) No part or phase of the Project A offshore works may commence until the MMO, in consultation with the MCA, has confirmed in writing that Bizco 2 has taken into account and, so far as is applicable to the relevant part or phase of the Project A offshore works, adequately addressed all the MCA recommendations in the OREI guidance that are appropriate to the Project A offshore works.
(a) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(b) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(2) No part or phase of the Project B offshore works may commence until the MMO, in consultation with the MCA, has confirmed in writing that Bizco 3 has taken into account and, so far as is applicable to the relevant part or phase of the Project B offshore works, adequately addressed all MCA recommendations contained in the OREI guidance that are appropriate to the Project B offshore works.
(3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(4) In this Requirement, “OREI guidance” means MCA document MGN543 “Offshore Renewable Energy Installations (OREIs) – Guidance on UK Navigational Practice, Safety and Emergency Response Issues” and its annexes (as amended from time to time).

---
Source: https://www.legislation.gov.uk/uksi/2015/1592/schedule/1/paragraph/16 (the official version)
Page: https://openlegislation.uk/dogger-bank-teesside-a-and-b-offshore-wind-farm-order-2015/schedule-1/paragraph-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.