# The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015, Paragraph 23: Fencing and other means of enclosure

Extent: E+W+S

(1) No stage of the onshore works may commence until written details of all proposed permanent and temporary fences, walls or other means of enclosure for that stage have been submitted to and approved by the relevant planning authority.
(2) All construction sites must remain securely fenced at all times during construction of the onshore works.
(3) Any temporary fencing must be removed on completion of the relevant work.
(4) Any approved permanent fencing in relation to the Project A converter station works must be completed before any part or parts of the relevant work is brought into use.
(4A) Any approved permanent fencing in relation to the Project B converter station works must be completed before any part or parts of the relevant work is brought into use.
(5) Fencing, walls and other means of enclosure must be provided in accordance with the approved details.
(6) For the avoidance of doubt, each set of submitted details approved under paragraph (1) of this requirement may cover one or more stages of the onshore works.

---
Source: https://www.legislation.gov.uk/uksi/2015/1592/schedule/1/paragraph/23 (the official version)
Page: https://openlegislation.uk/dogger-bank-teesside-a-and-b-offshore-wind-farm-order-2015/schedule-1/paragraph-23
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.