# The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015, Paragraph 24: Highway accesses

Extent: E+W+S

(1) No stage of the onshore works may commence until, for that stage, written details of the siting, design, layout and any access management measures for any new permanent or temporary means of access to or from a public highway to be used by vehicular traffic, or any alteration to an existing means of access to or from a public highway used by vehicular traffic, has, after consultation with the highway authority, been submitted to and approved by the relevant planning authority.
(2) No stage of the onshore works may commence until, for that stage, written details identifying the routes and accesses for operational maintenance has, following consultation with the highway authority, been submitted to and approved by the relevant planning authority.
(3) All highway accesses must be constructed, maintained and removed in accordance with the approved details.
(4) For the avoidance of doubt, each set of submitted details approved under paragraph (1) of this requirement may cover one or more stages of the onshore works.

---
Source: https://www.legislation.gov.uk/uksi/2015/1592/schedule/1/paragraph/24 (the official version)
Page: https://openlegislation.uk/dogger-bank-teesside-a-and-b-offshore-wind-farm-order-2015/schedule-1/paragraph-24
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.