# The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015, Paragraph 31: Control of artificial light emissions

Extent: E+W+S

(1) The Project A converter station works must not be brought into operation until a written scheme for the management and mitigation of artificial light emissions during the operation of the Project A converter station works has been submitted to and approved by the relevant planning authority.
(2) The approved scheme for the management and mitigation of artificial light emissions for the Project A converter station works must be implemented and maintained during the operation of the Project A onshore works.
(3) The Project B converter station works must not be brought into operation until a written scheme for the management and mitigation of artificial light emissions during the operation of the Project B converter station works has been submitted to and approved by the relevant planning authority.
(4) The approved scheme for the management and mitigation of artificial light emissions for the Project B converter station works must be implemented and maintained during the operation of the Project B onshore works.

---
Source: https://www.legislation.gov.uk/uksi/2015/1592/schedule/1/paragraph/31 (the official version)
Page: https://openlegislation.uk/dogger-bank-teesside-a-and-b-offshore-wind-farm-order-2015/schedule-1/paragraph-31
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.