# The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015, Paragraph 10


(1) Not less than 30 days before commencing the execution of any works of the type referred to in paragraph 8(2) that are near to, or will or may affect, any apparatus the removal of which has not been required by the undertaker under that sub-paragraph, and in all cases where such works are within 3,000 millimetres of any apparatus the removal of which has not been required by the undertaker under that sub-paragraph, the undertaker must submit to the owner or operator in question a plan, section and description of the works to be executed.
(2) Those works must be executed only in accordance with the plan, section and description submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by the owner or operator for the alteration or otherwise for the temporary or permanent protection of the apparatus, or for securing access to it, and the owner or operator must be notified of the timing of the works and afforded facilities to watch, monitor and inspect the execution of the works.
(3) Any requirements made by an owner or operator under sub-paragraph (2) must (except in circumstances where the requirements reasonably arise from the owner or operator watching, monitoring and inspecting those works) be made within 30 days beginning with the date on which a plan, section and description under sub-paragraph (1) are submitted to it and, where the works relate to the installation or construction of the authorised project, such requirements may require the protective measures referred to in sub-paragraph (2) to be retained in place at any time that the authorised project is installed.
(4) If an owner or operator, in accordance with sub-paragraph (3) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, this Part applies as if the removal of the apparatus had been required by the undertaker under paragraph 8(2).
(5) Nothing in this paragraph prevents the undertaker from submitting at any time or from time to time, but in no case less than 30 days before commencing the execution of any works, a new plan, section and description instead of the plan, section and description previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan, section and description.
(6) On the reasonable and evidenced request of an owner or operator affected by proposed works, the undertaker must extend the periods in this paragraph by a reasonable time.
(7) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency, but in that case the undertaker—
(a) must undertake the works in such manner as has regard to the potential lack of suitable temporary or permanent protection of the owner’s or operator’s apparatus;
(b) must give to the owner or operator in question, as soon as reasonably practicable, notice and a plan, section and description of the works; and
(c) must comply with sub-paragraph (2) so far as is reasonably practicable in the circumstances.

---
Source: https://www.legislation.gov.uk/uksi/2015/1592/schedule/12/part/6/paragraph/10 (the official version)
Page: https://openlegislation.uk/dogger-bank-teesside-a-and-b-offshore-wind-farm-order-2015/schedule-12/part-6/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.