# The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015, Paragraph 7


If an owner or operator considers that any proposed exercise by the undertaker of a power under this Order breaches paragraph 4 or 5 or if there is a dispute about the proposed insurance (including the terms or level of cover) to be provided under paragraph 6, before such a power may be exercised—
(a) the owner or operator may refer the matter to an expert for determination under paragraph 24; and
(b) the undertaker must not exercise the power concerned until that determination has been provided.

---
Source: https://www.legislation.gov.uk/uksi/2015/1592/schedule/12/part/6/paragraph/7 (the official version)