# The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015, Paragraph 24: Offshore maintenance plan

Extent: E+W+S

(1) The undertaker must, at least 4 months before commissioning the licenced activities, submit for written approval by the MMO an offshore maintenance plan based on the maintenance assessed in accordance with the environmental statement in the outline offshore maintenance plan.
(2) An update to the offshore maintenance plan must be submitted for approval every 3 years, or sooner in the event of any proposed major revision to planned maintenance activities or the adoption of any new technologies or techniques applicable to programmed maintenance.
(3) Maintenance must be carried out in accordance with the approved offshore maintenance plan.

---
Source: https://www.legislation.gov.uk/uksi/2015/1592/schedule/8/paragraph/24 (the official version)
Page: https://openlegislation.uk/dogger-bank-teesside-a-and-b-offshore-wind-farm-order-2015/schedule-8/paragraph-24
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.