# The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015, Paragraph 12: Layout rules

Extent: E+W+S

(1) The positions of wind turbine generators and offshore platforms must be arrayed in accordance with the parameters applicable to Work No. 1B specified in the Conditions and the principles in section 5.2 of Chapter 5 of the environmental statement.
(2) The construction of wind turbine generators or offshore platforms must not commence until the array location and layout plan has been agreed.
(3) The construction of wind turbine generators and offshore platforms must be carried out in accordance with the array location and layout plan.

---
Source: https://www.legislation.gov.uk/uksi/2015/1592/schedule/9/paragraph/12 (the official version)
Page: https://openlegislation.uk/dogger-bank-teesside-a-and-b-offshore-wind-farm-order-2015/schedule-9/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.